I have a graph working properly but want to plot the data -1d. WhenI type in 1d it sets the data 1 day forward. When I type -1d it does not except the format. Any suggestion as to getting the data to plot for the prior day using the time delay option?

Posted on
Sat Dec 08, 2018 4:16 pm
vtmikel offline
Posts: 643
Joined: Aug 31, 2012
Location: Boston, MA

Re: Time shift

Did the suggestion durations in the top right not work for your graph?

I tried this and it worked for me: &from=now-1d%2Fd&to=now-1d

Posted on
Sat Dec 08, 2018 6:52 pm
farberm offline
Posts: 393
Joined: Feb 24, 2008

Re: Time shift

Neither of them worked. When I enter them the box is outlined in red meaning not valid

Posted on
Sun Dec 09, 2018 9:38 am
farberm offline
Posts: 393
Joined: Feb 24, 2008

Re: Time shift

I must not be doing something correctly. I go to the panel and choose More, PanelJSON and go down to timeshift option. I change null to what you have on your reply . .... &from=now-1d%2Fd&to=now-1d... and hit the update button. It does not take into the JSON.

What am I doing wrong?

Also tried going to the edit panel and choose Time Range. Under Time shift I tried both -1d and &from=now-1d%2Fd&to=now-1d. Neither are accepted - Reads invalid Time shift on the graph

Posted on
Sun Dec 09, 2018 3:38 pm
siclark offline
Posts: 1960
Joined: Jun 13, 2017
Location: UK

Re: Time shift

This works for me. I have one chart of last 24 hours, then this setting gives me the 24 hours before that.

Image

Posted on
Sun Dec 09, 2018 4:26 pm
farberm offline
Posts: 393
Joined: Feb 24, 2008

Re: Time shift

I am trying to do "-1d" not 1d.

This is what I am trying to accomplish. I am reading water usage every day as 11:59 pm. That variable then gets posted. But since that value stay constant until the next evening at 11:59 pm it posts for the entire next day. I am trying to post it for the prior day to show the water usage on the day it was used.. When I insert 1d chart (first image) the chart gets moved but the data posts to the same day. See two images (the second image is without the 1d time shift

Example. Water usage 12/7 was 202 gallons. Posts as 202 gallons for 12/8. When I use time shift it just shifts the graph nut not the data posting date.
Attachments
Screen Shot 2018-12-09 at 5.19.58 PM.png
Screen Shot 2018-12-09 at 5.19.58 PM.png (31.85 KiB) Viewed 2178 times
Screen Shot 2018-12-09 at 5.18.46 PM.png
Screen Shot 2018-12-09 at 5.18.46 PM.png (30.78 KiB) Viewed 2178 times

Posted on
Sun Dec 09, 2018 4:43 pm
siclark offline
Posts: 1960
Joined: Jun 13, 2017
Location: UK

Time shift

I've think I understand, if I get you, you don't want these options. You need something in the actual data query.

The time shift functionality let's you shift the time that is shown compared to what is selected to compare previous day/week.

You want to adjust data to show against a different day to what it was recorded against? That is very different.


Sent from my iPhone using Tapatalk

Posted on
Sun Jan 06, 2019 10:55 am
vtmikel offline
Posts: 643
Joined: Aug 31, 2012
Location: Boston, MA

Re: Time shift

Also note that the time shift does not work on the Discrete panels. This is the primary reason for needing the "Minimum update frequency" setting in the plugin.